About

Continuous Improvement

To support Penn’s Second-Year Experience and maintain a high-quality on-campus living environment, the University continues to make significant investments in existing College Houses and campus infrastructure. Information on these initiatives—and their impact on the on-campus living experience—is provided below.

On-Campus Projects

1920 Commons Renovations

Penn Dining is creating a space that is welcoming, functional, and responsive to student needs. When complete, 1920 Commons will offer improvements designed to support convenience, comfort, and community. Demolition work will begin Summer 2026 and the fully renovated 1920 Commons will be complete Winter 2029.


Residential impact to academic year 2026–2027:

Noisy work will occur 8 a.m. to 5 p.m. through December 2028. This noise will be heard in Harnwell College House.

Please review the schedule and timeline below to see residential impact to students.

 

Estimated DateActivityDescriptionResidential Impact
May 2026 through August 2026Phase 1: Demolition The project includes limited demolition to create a new opening between 1920 Commons and the planned addition, along with interior pre-construction work to prepare the building ahead of the academic year. Loud demolition activity is expected for approximately four weeks beginning in mid-May. A temporary wall will be installed by June 7 to enclose the construction area, allowing operations to largely resume as normal thereafter. During this phase, the Starbucks seating area—including soft seating and the lower-level patio—will be closed.Demolition will be loud during working hours. Noise will be heard in both 1920 Commons and Harnwell College House.
October 2026 through November 2027Phase 1B: Construction of Addition This phase includes construction of the new addition, which will ultimately serve as the new entrance to 1920 Commons. Throughout construction, Starbucks and Gourmet Grocer will remain open, and summer 2027 operations are expected to continue out of 1920 Commons. A temporary Grab-and-Go location will be constructed by the end of Phase 1B and is scheduled to open on the first day of classes in January 2028.Construction will be loud during working hours. Noise will be heard in both 1920 Commons and Harnwell College House.
December 2027 through July 2028Phase 2: Renovation of the Lower Levels This phase includes renovation of the lower level (Starbucks area) and first level (Gourmet Grocer) of 1920 Commons. Upon completion, the space will feature an enhanced Gourmet Grocer, a new retail location, a coffee shop, and new meeting and study spaces. During construction, a temporary Grab-and-Go—offering exchange and grocery items, including halal and kosher options—will operate from the lower level of the new addition. AYCTE will remain operational throughout the academic year and will close during the summer.Noisy work will take place inside of 1920 Commons.
May 2028 through November 2028Phase 3: Renovation of AYCTE cafe This phase includes the closure and renovation of the all-you-care-to-eat cafe, with operations supported through various on-site operations.  Noisy work will take place inside of 1920 Commons.

 

On-Campus Projects

Harrison and Harnwell Elevators Modernization

All four elevators in Harrison and Harnwell will be replaced and fully modernized between September 2025 and July 2027. This work will improve reliability, reduce wait times, and create a smoother ride experience overall.

To minimize disruption, we’ll modernize one elevator at a time in each building, keeping three elevators operating in each High Rise throughout every phase of the project.


Residential impact to academic year 2026–2027:

One elevator in each building will be down at a time. This may increase elevator wait times. Minimal noisy work is expected, and will occur 8 a.m. to 5 p.m.

Please review the schedule and timeline below to see residential impact to students.

 

Estimated DateActivityDescriptionResidential Impact
September 2025 through February 2026Modernization of one elevator in each buildingNew cables, mechanical systems, and cabsDelayed travel time, possible short term elevator outages, corridor diversion when pulling new cables, minimal noise impact.
March 2026 through July 2026Modernization of one elevator in each buildingNew cables, mechanical systems, and cabsDelayed travel time, possible short term elevator outages, corridor diversion when pulling new cables, minimal noise impact.
September 2026 through January 2027Modernization of one elevator in each buildingNew cables, mechanical systems, and cabsDelayed travel time, possible short term elevator outages, corridor diversion when pulling new cables, minimal noise impact.
February 2027 through July 2027Modernization of one elevator in each buildingNew cables, mechanical systems, and cabsDelayed travel time, possible short term elevator outages, corridor diversion when pulling new cables, minimal noise impact.

 

On-Campus Projects

Quad Renovation

Renovations to the three College Houses in the historic Quadrangle began in May 2023 and conclude August 2026.  The work will include roof and window repair and replacement, façade repair, interior finishes and bathroom reconfiguration, elevator upgrades, chimney lining and reconstruction, mechanical and electrical system replacement, and College House program space improvements.

 

Residential impact to academic year 2026–2027:

The Quad renovation will be complete. There will be no impact to the on-campus living experience.

For a more detailed timeline, please review the chart below.

 

 

Estimated DateActivityDescriptionResidential Impact
Late March through April 26, 2023Scaffolding constructionScaffolding will be put up in the interior courtyards of Graduate, Bishop White, Birthday and Rodney, as well as the South side of McIlhenney, Ward and Warwick (outside of the moat) of Riepe College House for roof repair/replacement, chimney repairs, and exterior masonry repointing. Scaffolding will also be put up along the east facade of Morris and Bodine on the Junior Balcony. This work will improve the building envelope, reducing leaks and humidity impacting the interior.Work will be loud at times. Installation of scaffolding will be in front of student windows. Students are encouraged to keep windows and blinds closed during this period. Work will cease before study days and final exams. Weekly updates will be sent out about upcoming work. 

May 2023-August 2024

Riepe College House closed for renovations

Replacement and upgrades to mechanical, plumbing, and HVAC systems/fan coil units

Renovation of common area spaces, lounges, club room, study rooms, House Office, bathrooms

Replacement/refinishing of flooring in corridors and student rooms

Painting in public spaces and student rooms

Removal of popcorn ceilings

Repair/replace windows

Replace electrical switchgear

Add elevator in Provost Tower/Graduate area of Riepe

New furniture in student rooms and common spaces

New room and directional signage

This work will modernize mechanical, electrical, and plumbing systems.

Improvement of student social and study spaces, as well as refresh of student room.

New bathrooms that will allow for more privacy in stalls and shower areas.

Improved accessibility with additional elevators.

Work will be contained to the renovation area. During the construction period there will be no access to Riepe College House. Noise will be restricted to the renovation area, but depending on the work, could have minor impact on the surrounds areas.
Mid-Spring Semester 2024Scaffolding constructionScaffolding will be put up in the interior courtyards of Ware College House for roof repair/replacement, chimney repairs, and exterior masonry repointing. This work will improve the building envelope, reducing leaks and humidity impacting the interior.Work will be loud at times. Installation of scaffolding will be in front of student windows. Students are encouraged to keep windows and blinds closed during this period. Work will cease before study days and final exams.

May 2024-August 2025

Ware College House closed for renovations

Replacement and upgrades to mechanical, plumbing, and HVAC systems/fan coil units

Renovation of common area spaces, lounges, club room, study rooms, House Office, bathrooms

Replacement/refinishing of flooring in corridors and student rooms

Painting in public spaces and student rooms

Removal of popcorn ceilings

Repair/replace windows

Replace electrical switchgear

Add elevator in Memorial Tower

New furniture in student rooms and common spaces

New room and directional signage

This work will modernize mechanical, electrical, and plumbing systems.

Improvement of student social and study spaces, as well as refresh of student room.

New bathrooms that will allow for more privacy in stalls and shower areas.

Improved accessibility with additional elevators.

Work will be contained to the renovation area. During the construction period there will be no access to Ware College House. Noise will be restricted to the renovation area, but depending on the work, could have minor impact on the surrounds areas.

May 2024-August 2025

McClelland closed for renovations

Replacement and upgrades to mechanical, plumbing, and HVAC systems

Rework stairs between the first and second floor

Updated seminar room

Updated fitness center

Redesigned skylight at Junior Balcony with upgraded pavers

Window replacement 

New paint, flooring, lighting

New music practice rooms

New furniture

Updated finishes in the dining cafe

Renovate the non-dining spaces.

Update programming and communal spaces.

Repair waterproofing on the Junior Balcony.

Refresh dining finishes. 

Work will be contained to the renovation area. During the construction period there will be no access to McClelland. Dining and package lockers will be relocated. Noise will be restricted to the renovation areas, but depending on the work, could have minor impact on the surrounding areas.
Mid-Spring Semester 2025Scaffolding constructionScaffolding will be put up in the interior courtyards of Fisher Hassenfeld College House for roof repair/replacement, chimney repairs, and exterior masonry repointing. This work will improve the building envelope, reducing leaks and humidity impacting the interior.Work will be loud at times. Installation of scaffolding will be in front of student windows. Students are encouraged to keep windows and blinds closed during this period. Work will cease before study days and final exams.

May 2025-August 2026

Fisher Hassenfeld College House closed for renovations

Replacement and upgrades to mechanical, plumbing, and HVAC systems/fan coil units

Renovation of common area spaces, lounges, club room, study rooms, House Office, bathrooms

Replacement/refinishing of flooring in corridors and student rooms

Painting in public spaces and student rooms

Removal of popcorn ceilings

Repair/replace windows

New furniture in student rooms and common spaces

New room and directional signage

This work will modernize mechanical, electrical, and plumbing systems.

Improvement of student social and study spaces, as well as refresh of student room.

New bathrooms that will allow for more privacy in stalls and shower areas.

Work will be contained to the renovation area. During the construction period there will be no access to Fisher Hassenfeld College House. Noise will be restricted to the renovation area, but depending on the work, could have minor impact on the surrounds areas.
On-Campus Projects

Student Performing Arts Center (SPAC)

As announced in June 2023, SPAC––the new student-centered performing arts venue––is to be built along Woodland Walk and 33rd Street. SPAC will provide multiple flexible spaces for teaching, rehearsals, and student performances.

SPAC is being built between Lauder College House and Hill College House

Residential impact to academic year 2026–2027:

Noisy work will occur 8 a.m. to 5 p.m. through July of 2026. Low noise work (landscaping) will occur in Fall 2026.

Please review the schedule and timeline below to see residential impact to students living in Hill and Lauder. 

 

 
Estimated DateActivityDescriptionResidential Impact
July 2024MobilizationSetting up construction fences, sidewalk closure, job trailers, land clearing will commence.

West 33rd Sidewalk and parking lane will be shut down. Fencing and trailer noise will include trucks and pneumatic post drivers. Land clearly will utilize builldozer and truck haulers. Noise level will be: medium.

 

August 2024DemolitionStructure removalsJack hammer and concrete saw cutting noise. Noise level will be high. There will be no impact to move-in activities.
September 1 through October 18, 2024Sheeting & Shoring/ExcavationSoil removal and earth retaining workEarth digging and removal equipment will produce loud noise. Sheating and shoring equipment will provide pounding of steel soilder beams. Noise level will be high.
September 30 , 2024 through January 15, 2025Underground UtilitiesInstall Storm and Sanitary LinesTrench excavation and pipe installation. Noise level will be medium to high.
October 15 through December 15, 2024Cassions and FoundationsDrill cassions excavate slabs and footings. Pour concrete in slabs and footings.Drill rigs and excavator equipment. Noise level will be high.
December 15, 2024 through June 24, 2025Structural Steel Building FrameSteel erection with crane operation and steel truck deliveries.Crane and erection operations ad steel deliveries. Noise level will be medium to high.
August 2025 through December 2025Structural Concrete/FireproofingDeck pours with concrete trucks & fireproofing of the structural systemLonger work hours on concrete pour days, Saturdays for fireproofing
October 2025 through April 2026Facade EnclosureGround floor curtainwall installation, exterior framing & sheathingMed to high noise impact, working Saturdays to finish as quick as possible
February 2026 through April 2026RoofingInstallation of the roofing systemLow to med noise
May 2026 through Aug 2026Terracotta Rain ScreenInstallation of the exterior finish of buildingMed noise, work adjacent to Woodland Walk will require closures
March 2026 through April 2026Traffic Signal UpgradesAddition of buttons & programming to the lights at 33rd & ChestnutWill require corner to be shutdown to get conduit installed/concrete repoured
April 2026 through July 2026SiteworkRain Garden, irrigation & landscaping to be installed (trees/plantings completed in Oct/Nov 2026)Low to med noise
Nov 2025 through April 2026MEPFP Rough InInstallation of the infrastructure to the building by mechanical, plumbing, electrical and fire protection subsMed noise
March 2026 through December 2026Interior WorkFrom drywall to finishes of the project including all theatre equipment, furniture, paint, flooring, etc.No impact
Fall 2026LandscapingPlanting and other landscaping around the exterior of the buildingLow noise

 

On-Campus Projects

Completed Projects

 Hill House is a vibrant residential community with a special commitment to first year students — a commitment shared by an energetic group of upper class students who eagerly choose to live in Hill for its leadership opportunities. The resident Faculty Director, House Fellows, House Director and Graduate Associates are dedicated to providing residents with personal and professional assistance to successfully transition to University life both intellectually and socially.

In June 2016, Penn began a major renovation to Hill, to be completed in time for August 2017 Move In.

Hill College House

 

When Hill first opened in 1961 as a Penn's women's dormitory, the Pennsylvania Gazette ran a multi-page photo-essay headlined "A Starkly-Plain Outside But a Wow! Inside." One charmed resident likened the airy interior -- with its dramatic atrium, "wrought-iron balustrades (and) louvered shutters," and "green tropical plants" to being "in a Mediterranean town." Penn has demonstrated its commitment to providing a unique and dynamic residential experience to future residents of Hill through extensive renovation that should see the house through another 50 years of living and learning.

 

Hill Modernization 2016-2017

Hill College House 3


A complete building renovation at Hill will address maintenance and system upgrades needed for a modern College House. Work Includes:

  • Conversion of all suite bathrooms to individual restrooms and shower rooms
  • Renovation to all bedrooms and common spaces
  • New room and common area furnishings, fixtures, and fit out
  • All spaces will be air conditioned, including student rooms and the atrium area, along with other upgrades to mechanical and electrical systems
  • Major upgrades to dining areas and central kitchen, including expansion of the commissary serving Penn Dining
  • Repointing of the masonry envelope
  • Restoration of all windows
  • Installation of new room and curtainwall glazing facing the central atrium

Cost, Schedule, and Resources

  • Total Project Cost: $80M Hill College House Resources & Information
  • Construction: May 2016 - July 2017
  • The Pennsylvania Gazette, February 2016
     

Hill 2

 

History and Preservation

Designed by Eero Saarinen in 1958, Hill College House is an internationally recognized architectural landmark located at the corner of 33rd and Walnut Streets. Originally a women's dormitory, the building's entry features an allegorical bridge over an ivy filled "moat" and its surrounding spiked metal fence. The living spaces, including five floors of double bedroom accommodates 500 students. Student lounges and seminar rooms are built around a vast central atrium that overlooks a dining area on the lower level. The arrangement is reminiscent of a Mediterranean village where residents live around a central square or plaza where they gather to celebrate, share their news and mark milestones of the year. Other iconic Saarinen designs include the St. Louis Gateway Arch, Washington Dulles Airport in Washington, D.C., Ingalls Rink and the Morse and Ezra Stiles Colleges at Yale University. He also designed furnishings for his projects, including the well known mid-century "Tulip" and "Womb" chairs. Hill College House is named for Robert C. Hill, an 1889 graduate of the College of Arts and Sciences and university benefactor.
 

More Hill College House Links:

  

Students on Campus

 

 

"Generations of Penn students will call this extraordinary place home." Dr. Amy Gutmann

 

Lauder House Project

 

Lauder College House Site, August 2015
Lauder College House project photos will be periodically posted throughout the construction process.

 

 

 

About the Lauder College House

  • The first signature residential building on Penn's campus specifically designed and built to maximize the College House experience.

 

  • Built to accommodate the intellectual, cultural, and social activities that have become the hallmark of Penn's College Houses.

 

  • Will frame the gateway to campus at 33rd and Chestnut Streets and will be adjacent to 34th Street, Chestnut Street, and the 125 Years of Women at Penn Walkway.

Click on arrows below for full details.

 

  • Residential Design Features

    • Will house 350 students in multiple-bedroom suites in 1- 6 bedroom arrangements with private bathrooms

    • Major programmatic spaces around a central courtyard that serves the population of the building and encourages all residents to engage in the life of the House

    • Large living room designed as multipurpose space for a variety of events

    • A media center will be located on the first floor

    • Two seminar rooms with classroom instruction technology

    • Two music practice rooms for lessons and student practice

    • Community kitchens will allow residents to cook meals for themselves

    • Lounge areas on every floor

 

  • Dining Design Features

    • The dining program in the Lauder College House will be a hybrid on an 'a la carte menu' for breakfast, lunch, and late night service and a dinner service will consist of All-You-Care-To-Eat with an option for family style dining

    • The display cooking island will be a major focal point of the facility and feature a wok range, and grille for both vegan and non-vegan items

    • The focus will be on community dining. Dinner service is envisioned to be available in family style and include composed salads of the day, choice of a few entrees, vegetable, starch, dessert, and beverages

 

  • Sustainability

    • The project was designed and constructed to achieve the targeted LEED Silver Certification for new construction through the US Green Building Council

    • A large open landscaped lawn area

    • A series of green roofs and a below grade cistern will manage the storm water

    • Low-flow and low consumption plumbing fixtures are anticipated to achieve a reduction in water usage of 30-40% over the baseline

 

  • College House System

    • 52% of our undergraduates reside with the College House System

    • 99% of the first year class and 50% of the second year class reside in the College House System

    • Third and fourth year students comprise the remaining 30% of College House residents with equal representation from both classes

    • The Lauder College House will provide the premier on-campus living experience with a flexible dining commons and private courtyard, similar to the Quadrangle's spaces in scale and feel

 

  • Project Team

    • Design Team: Bohlin Cywinski Jackson is a Philadelphia based architectural office. They have received more than 460 regional, national, and international awards for design. They have designed projects such as The Liberty Bell Center on Independence Mall and Apple stores around the world

    • Construction Management Team: INTECH Construction was founded in 1986 and is a Philadelphia based construction manager and general contractor. They have completed significant College House renovations at Penn as well as the National Museum of American Jewish History

 

  • Project Budget and Schedule

    • Budget: $127 million

    • Schedule: Completion 2016
      • Fall 2013                         Early site work begins

        January 2014                Construction begins

        July 2016                        Construction complete

        August 2016                 Move in for residents

 

Click here to see pictures of the Lauder College House groundbreaking celebration.

For information about Lauder College House as it is today visit our Living Options page.

The University has awarded Greystar, a global firm specializing in rental housing including the collegiate marketplace, with a contract to oversee the renovation and management of Sansom Place East (SPE). The agreement, which was presented to Penn’s Board of Trustees at its June 2021 meeting, awarded Greystar a 75-year land-lease agreement under which the firm will completely renovate and subsequently manage the property which will continue to be used primarily as graduate housing.

The award was the completion of a long-term planning project to evaluate on and off-campus housing for graduate students, which included data gathering, surveys and focus groups and a detailed analysis of the current housing market in University City and the region. The results of this effort highlighted that despite the University’s investment in SPE ($14M between 2005 - 2015), the types of apartments and amenities provided were no longer aligned to the needs of the today’s graduate students.

Ideally located, the redeveloped student housing will be only a block away from the Penn Law School; two blocks from both the Wharton School and the Graduate School of Education; and four blocks from the School of Engineering and Applied Science. Adjacent to the Sansom Place East property, the existing occupied commercial retail at street level and the Philadelphia Institute of Contemporary Art will remain open during construction.

Priority is given to Penn graduate and professional students through May 1, 2023. For more information, click here.

Building Project Outcome
Gregory College House HVAC Units

Resident rooms, corridors, and common areas will receive new HVAC units that will provide both heating and air-conditioning to these spaces. The windows in Gregory are being replaced and new roller shades are being installed in place of the existing metal blinds.

Gutmann College House

Construction of College House

New 430-bed building in Hamilton Village.